Project-to-Settlement SAP S/4HANA training
Manage project structures from WBS planning through execution, cost collection and settlement.
Prehľad procesu a biznis kontext
Project-to-Settlement connects WBS structures, networks, procurement, confirmations, revenue or investment handling and period-end settlement.
Learners can explain how project costs and revenues are planned, captured and settled to the right receiver.
End-to-end tok
- 1
Create project structure
CJ20NFiori aplikácia: Project Control
Vplyv na ACDOCA: Defines WBS and accountability.
- 2
Plan dates and costs
CJ40 / Easy Cost PlanningFiori aplikácia: Project Planning apps
Vplyv na ACDOCA: Creates baseline and budget context.
- 3
Execute procurement and work
ME21N / CN22Fiori aplikácia: Manage Project Procurement
Vplyv na ACDOCA: Posts commitments and actual costs.
- 4
Confirm activities
CN25 / CATSFiori aplikácia: Record Project Time
Vplyv na ACDOCA: Posts labor/activity actuals.
- 5
Settle project
CJ88Fiori aplikácia: Run Settlement
Vplyv na ACDOCA: Transfers costs/revenues to asset, cost center or profitability receiver.
Kľúčové tabuľky
| Table | Vysvetlenie |
|---|---|
| PROJ | Project definition data. |
| PRPS | WBS element master data. |
| AFVC | Network activities and operations. |
| COEP / ACDOCA | Project actual costs in controlling and Universal Journal reporting. |
| COBRB | Settlement rule data. |
Postup krok za krokom
Design the WBS for control
Create WBS levels that match reporting, responsibility and settlement needs.
Na čo si dať pozor: A WBS that is too detailed or too shallow makes control difficult.
Plan and budget early
Maintain cost plan, budget availability and dates before execution.
Na čo si dať pozor: Availability control issues are usually planning ownership issues.
Collect actuals consistently
Post procurement, time and activity confirmations against the correct WBS or network.
Na čo si dať pozor: Wrong account assignment makes project margin unreliable.
Close with settlement
Maintain settlement rules and run period-end settlement.
Na čo si dať pozor: Costs left on temporary project objects distort reporting.
Bežné chyby a riešenie problémov
Posting rejected by budget control
Pravdepodobná príčina: Budget is missing or availability control limit is exceeded.
Postup opravy: Review budget release, tolerance profile and assigned value.
Project costs settle to wrong receiver
Pravdepodobná príčina: Settlement rule or strategy is incorrect.
Postup opravy: Correct settlement rule and rerun test settlement.
WBS report misses actuals
Pravdepodobná príčina: Posting used wrong WBS, network or period.
Postup opravy: Trace source document and account assignment.
Rozdiely ECC a S/4HANA
S/4HANA keeps WBS and network fundamentals while improving project reporting and integration with Universal Journal dimensions.
Slovník
- WBS element
- Project structure element for planning, budgeting and reporting.
- Network activity
- Executable project activity with dates, resources and costs.
- Availability control
- Budget check that controls project spending.
- Settlement rule
- Definition of where project costs or revenues are transferred.