PM/EAM · Plant Maintenance / Asset Management

Maintenance-to-Settlement SAP S/4HANA training

Manage asset maintenance from notification through order execution, confirmation, completion and settlement.

Prozessueberblick und Geschaeftskontext

Maintenance-to-Settlement protects asset availability. It connects malfunction reporting, work planning, permits, spare parts, confirmations, technical completion and cost settlement.

Learners can follow a maintenance issue from notification to financial close and explain where operational and cost controls happen.

End-to-End-Ablauf

  1. 1

    Create notification

    IW21

    Fiori-App: Manage Maintenance Notifications and Orders

    ACDOCA-Auswirkung: No direct finance posting; captures problem and technical object.

  2. 2

    Plan maintenance order

    IW31 / IW32

    Fiori-App: Manage Maintenance Orders

    ACDOCA-Auswirkung: Plans labor, components and services.

  3. 3

    Release and execute work

    IW32

    Fiori-App: Maintenance Order Processing

    ACDOCA-Auswirkung: Allows confirmations and goods issues.

  4. 4

    Confirm work

    IW41

    Fiori-App: Confirm Maintenance Order

    ACDOCA-Auswirkung: Posts labor/activity and consumed material costs.

  5. 5

    Complete and settle

    IW32 / KO88

    Fiori-App: Technical Completion; Settlement

    ACDOCA-Auswirkung: Moves costs to receiver and closes order lifecycle.

Wichtige Tabellen

TableErklaerung
QMELMaintenance notification header and problem data.
AUFKOrder master data shared across order types.
AFIHMaintenance order header data.
AFVCOrder operations and work execution steps.
RESBMaterial reservations for spare parts.

Schritt-fuer-Schritt-Anleitung

Capture the failure clearly

Record equipment, functional location, damage, cause and priority.

Achten Sie auf: Poor notification coding weakens reliability analytics.

Plan work and materials

Add operations, work center, duration, components and permits.

Achten Sie auf: Releasing an underplanned order shifts risk to technicians.

Confirm actuals

Record time, technical findings, measurements and spare parts.

Achten Sie auf: Confirmations are the evidence behind cost and reliability reports.

Complete technically and financially

Set technical completion, review open reservations and settle costs.

Achten Sie auf: Technical completion does not replace financial settlement.

Haeufige Fehler und Fehlerbehebung

Order cannot be released

Wahrscheinliche Ursache: Missing planning data, permit, user status or budget check.

Loesungsweg: Review status profile, permits and order logs.

Spare part is unavailable

Wahrscheinliche Ursache: Reservation was late, stock is missing or MRP did not procure.

Loesungsweg: Check reservation, stock/requirements list and procurement proposal.

Order still has open cost

Wahrscheinliche Ursache: Settlement rule or settlement run is missing.

Loesungsweg: Maintain receiver and execute settlement with log review.

ECC zu S/4HANA Unterschiede

S/4HANA provides Fiori apps for managing notifications and orders, while core order lifecycle concepts remain familiar from ECC.

Glossar

Notification
Record of a malfunction, request or maintenance event.
Maintenance order
Executable work package for planning and controlling maintenance.
Technical completion
Status showing maintenance work is complete.
Settlement
Transfer of collected order costs to the final receiver.

Wissenstest

Schließen Sie den Test mit mindestens 70 % ab, um das Zertifikat freizuschalten.