PM/EAM · Plant Maintenance / Asset Management

Maintenance-to-Settlement SAP S/4HANA training

Manage asset maintenance from notification through order execution, confirmation, completion and settlement.

Přehled procesu a business kontext

Maintenance-to-Settlement protects asset availability. It connects malfunction reporting, work planning, permits, spare parts, confirmations, technical completion and cost settlement.

Learners can follow a maintenance issue from notification to financial close and explain where operational and cost controls happen.

End-to-end tok

  1. 1

    Create notification

    IW21

    Fiori aplikace: Manage Maintenance Notifications and Orders

    Dopad na ACDOCA: No direct finance posting; captures problem and technical object.

  2. 2

    Plan maintenance order

    IW31 / IW32

    Fiori aplikace: Manage Maintenance Orders

    Dopad na ACDOCA: Plans labor, components and services.

  3. 3

    Release and execute work

    IW32

    Fiori aplikace: Maintenance Order Processing

    Dopad na ACDOCA: Allows confirmations and goods issues.

  4. 4

    Confirm work

    IW41

    Fiori aplikace: Confirm Maintenance Order

    Dopad na ACDOCA: Posts labor/activity and consumed material costs.

  5. 5

    Complete and settle

    IW32 / KO88

    Fiori aplikace: Technical Completion; Settlement

    Dopad na ACDOCA: Moves costs to receiver and closes order lifecycle.

Klíčové tabulky

TableVysvětlení
QMELMaintenance notification header and problem data.
AUFKOrder master data shared across order types.
AFIHMaintenance order header data.
AFVCOrder operations and work execution steps.
RESBMaterial reservations for spare parts.

Postup krok za krokem

Capture the failure clearly

Record equipment, functional location, damage, cause and priority.

Na co si dát pozor: Poor notification coding weakens reliability analytics.

Plan work and materials

Add operations, work center, duration, components and permits.

Na co si dát pozor: Releasing an underplanned order shifts risk to technicians.

Confirm actuals

Record time, technical findings, measurements and spare parts.

Na co si dát pozor: Confirmations are the evidence behind cost and reliability reports.

Complete technically and financially

Set technical completion, review open reservations and settle costs.

Na co si dát pozor: Technical completion does not replace financial settlement.

Běžné chyby a řešení problémů

Order cannot be released

Pravděpodobná příčina: Missing planning data, permit, user status or budget check.

Postup opravy: Review status profile, permits and order logs.

Spare part is unavailable

Pravděpodobná příčina: Reservation was late, stock is missing or MRP did not procure.

Postup opravy: Check reservation, stock/requirements list and procurement proposal.

Order still has open cost

Pravděpodobná příčina: Settlement rule or settlement run is missing.

Postup opravy: Maintain receiver and execute settlement with log review.

Rozdíly ECC a S/4HANA

S/4HANA provides Fiori apps for managing notifications and orders, while core order lifecycle concepts remain familiar from ECC.

Slovník

Notification
Record of a malfunction, request or maintenance event.
Maintenance order
Executable work package for planning and controlling maintenance.
Technical completion
Status showing maintenance work is complete.
Settlement
Transfer of collected order costs to the final receiver.

Knowledge check